NUCLEAR POWER CORPORATION OF INDIA LIMITED
ANNUAL REPORT 2010-2011
CHAIRMAN'S STATEMENT
We are about to enter 25th year of formation of NPCIL. In these years we
have established strong foundation of Company, based on excellent corporate
governance with overriding priority on nuclear safety, transparency and
unmatched human resource which is the backbone of our performance. Today,
the Company is at a threshold of taking off to greater heights and to make
a difference from here, we will realise the dream of multiplication of
nuclear power in the country and not just addition.
On the front of domestic Pressurised Heavy Water Reactor programme, the
units under operations demonstrated steady operations with high
availability and very long continuous operations of the units. Renovation &
Modernisation activities viz. En-masse Coolant Channel Replacement (EMCCR),
En-masse Feeder Replacement (EMFR) together with upgrades
have been completed at NAPS-2 and KAPS-1 and these reactors were
synchronised to the grid during the year. Calandria vault water leakage at
KAPS-1 reactor was successfully repaired using innovatively designed remote
welding technique.
With the commissioning of Kaiga-4 (220 MW) during the year, the number of
Nuclear Power Reactors in operation in the country has increased to 20 with
a total installed capacity of 4,780 MW including RAPS-1 (100 MW) owned by
the Government and operated by NPCIL.
With this NPCIL has placed India among top six countries of the world which
operate 20 or more reactors.
As per separation plan, Nuclear Power Plants RAPS-3&4, RAPS-5&6, KAPS-1&2,
were brought under IAEA safeguards domain making it possible to fuel them
with imported fuel. With this effort, now operating reactors under
safeguards are operating at 100% full power, whereas remaining 10 reactors
were operating at 70% full power average.
The Kudankulam Project under construction has recorded excellent progress
with Unit-1 and Unit-2 achieving 98% and 93% completion respectively. In
unit-1, significant milestones on the commissioning front were achieved
during the year, including completion of 'Hydro Test (Strength Test) of
Primary Circuit at 24.5 MPa of the Nuclear Steam Supply System and
Secondary Circuit at 10.8 MPa' and 'Strength and Leak Rate Test of Reactor
Building Containment'. The preliminary works for carrying out the 'hot run'
test at designed parameters were also completed.
Your Company launched first twin reactor units of 700 MW series at Kakrapar
namely KAPP-3&4, marked by the First Pour of Concrete on 22nd November 2010
after receiving regulatory clearances from Atomic Energy Regulatory Board.
Since then, various project activities were being executed expeditiously
and simultaneously for all main plant buildings and residential colony. The
manufacturing of all equipment with long delivery period is in full swing
and all main plant works orders have been awarded for completion of KAPP-
3&4 in the year 2016.
The first pour of concrete for two additional 700 MW PHWRs at RAPP-7&8 was
achieved on 18th July 2011 after receiving required regulatory clearances.
Earlier, the contract for Main Plant Civil Works was awarded. The
excavation of Reactor Building area has been completed and purchase orders
for all major long delivery items have been placed.
During March 2011, a significant event of fuel damage at an overseas plant
was reported as an aftermath of a natural event of extreme nature. As part
of safety culture of your Company, it was decided promptly to set up
several taskforces of technical experts to revisit the safety of Indian
NPPs and to review the margins considering the extreme natural events on a
deterministic basis. Even though the result of review was encouraging, not
to be complacent in any way, we have decided to augment/introduce several
features, like initiation of automatic reactor trip on sensing of seismic
activity in plant area, additional reactor cooling water arrangements and
motive force from an additional air cooled emergency diesel generator. The
outcomes of these reviews have also been made public. Further, your Company
has been in constant communication with several international organisations
to share the observations and recommendations on the above accident on day
to day basis, so that the best nuclear industry safety practices are
considered for emulation in NPCIL as they evolve.
Under international civil nuclear cooperation, your Company is working
towards collaboration with reputed nuclear vendors to accelerate the growth
of nuclear power and to add Light Water Reactors to quickly increase
generation capacities in India. The Kudankulam Project Unit-3&4 is an
expansion of Unit-1&2, being implemented with cooperation from Russian
Federation (RF) within the framework of the Inter Governmental Agreement
signed between Russian Federation and India signed in December 2008. A
contract for the first priority design works to carry out initial design
activities has been signed with Atomstroyexport and the work is in
progress. The various pre-project activities were also completed. Techno-
commercial discussions in respect of 2 x 1000 MW VVERs at KKNPP-3&4 with
Atomstroyexport are in the advanced stages of finalisation.
The land for Jaitapur NPP has been acquired and handed over to NPCIL by the
District Administration, Ratnagiri, Maharashtra. Agreement for
Rehabilitation of Project Affected Families of JNPP has been signed between
NPCIL and Government of Maharashtra. Pre-project activities viz. geo-
technical investigations, construction of property-cum-boundary wall of
Plant Site and master plan for residential complex are in progress.
Further, the General Framework Agreement and Early Work Agreement between
NPCIL and AREVA, France have been signed for implementation of EPR at
Jaitapur Site. Techno-commercial discussions with AREVA in respect of 2 x
1650 MW EPR units at Jaitapur Site are in advanced stage of conclusion.
Earlier, the Government of India has given 'In-principle' approval for five
new sites; two for indigenous PHWRs and three for LWRs based on foreign
cooperation. The pre-project activities at new sites are in progress. These
include establishment of the NPCIL offices in nearby towns, start of
Environment Impact Assessment studies for MoEF clearance, studies/ surveys
for arriving at the design inputs required for regulatory clearance, steps
for obtaining Siting Consent from the regulator, public awareness
programmes and actions for land acquisition to ready the sites for project
construction within shortest time. The land acquisition applications for
issuance of Section 4 notification under Land Acquisition Act, 1894 have
been already submitted to the respective District Authorities in Haryana,
Gujarat, Madhya Pradesh and Andhra Pradesh.
Being a national utility company operating nuclear power plants, we
participated in 5th Review Meeting of contracting parties of Convention of
Nuclear Safety at Vienna to demonstrate fulfilment of its primary
responsibility and obligation of maintaining safety as overriding priority,
while maximising the production to meet nation's electricity demand. The
safety record of over 330 reactor years of long operating experience was
well recognised by contracting parties.
I would also like to confirm that the Company has complied with the
Corporate Governance Guidelines issued by the Authorities.
Your CMD continued to be on worldwide governing board of World Association
of Nuclear Operators (WANO). We have been offering our operating plants for
international peer reviews and the plants at the verge of startup are
planned to be offered for pre-startup peer reviews to maintain and enhance
safety and reliability of our NPPs in line with best standards prevailing
in the world elsewhere.
I am sure that with continued support of Department of Atomic Energy and
its units, our customers and various government ministries, we will be able
to increase production of the Company to about 32,000 million kWh next
year. Members on board of the Company have immensely contributed, guided
and encouraged for all round improvement in functioning of your Company.
Finally, we proudly would like to put on record the culture of overriding
priority of nuclear safety and also the Parivar culture within Company
which has made this Company unique. It is now the time that I move on to
the Director's Report, Balance Sheet and Profit and Loss Account as on 31st
March 2011 for your consideration, approval and adoption.
S.K. Jain
Chairman & Managing Director
Place: Mumbai
Date : 7th September 2011