NUCLEAR POWER CORPORATION OF INDIA LIMITED
ANNUAL REPORT 2010-2011
DIRECTOR'S REPORT
Dear Stakeholders,
Your Directors have immense pleasure in presenting the twenty-fourth Annual
Report of the Company, together with the Audited Accounts for the year
ended 31st March 2011.
PERFORMANCE HIGHLIGHTS:
A summary of the Company's Financial Results is given below:
(Rs. in crore)
As at As at
Financial Results 31st March 2011 31st March 2010
Sale of Electrical Energy 6016 3807
Other Income 882 672
TOTAL INCOME 6898 4479
Operating & Maintenance 3680 2629
Expenditure
Interest 662 441
Depreciation 868 721
TOTAL EXPENDITURE 5210 3791
Profit for the year 1688 688
Prior period adjustments (1) (214)
Profit Before Tax 1687 474
Provision for Taxation 311 58
Profit After Tax 1376 416
Add: Balance brought 1122 981
forward from previous year
Balance available for 2498 1397
Appropriations
a) Interim Dividend 150 150
b) Tax on Interim Dividend 25 25
c) Proposed Dividend 263 -
d) Tax on proposed Dividend 44 -
e) Transfer to General Reserve 500 100
f) Balance carried to Balance Sheet 1516 1122
Earning per Share in RS. 136 41
(Equity share having face
value of Rs.1000/- each)
The Company has achieved higher average capacity factor of about 71% as
against 61% for the previous year. The use of imported fuel for reactors
under safeguards (1840 MW) and improved domestic fuel availability for
reactors fuelled by domestic uranium (2840 MW) resulted in higher capacity
utilization. The year under report recorded the highest nuclear power
generation since the inception of the Company. Electricity generation, as
per the billing cycle, in 2010-11 has been 26469 Million kWh (MUs) as
against 18798 MUs in 2009-10 showing an increase of 41%. The revenue
realization has been maintained at a high level of 99%.
The Department of Atomic Energy (DAE) has issued revised tariff norms for
determining tariff for sale of electricity by Atomic Power Stations, vide
notification dated 8th December 2010. The tariffs, based on revised norms
are effective from 1st July 2010 for all atomic power stations and are to
remain effective for 5 years. However, the revised tariffs, as per new
tariff norms, have not yet been notified. Pending such notification, the
revenue for the year has been determined as per existing tariff / on
provisional basis as per practice of the Corporation.
Renovation & Modernization activities viz. Enmasse Coolant Channel
Replacement (EMCCR), Enmasse Feeder Replacement (ENFR) together with
upgrades have been completed at NAPS-2 and KAPS-1 and these reactors were
synchronized to the grid during the year.
With the commissioning of Kaiga-4 (220 MW) during the year under report,
the number of Nuclear Power Reactors in operation in the country has
increased to 20 with a total installed capacity of 4780 MW including RAPS-1
(100 MW) owned by the Government and operated by NPCIL.
The revenue from sale of power generated from wind farm with an installed
capacity of 10 MW at Kudankulam during the year was Rs. 6.42 crore as
against Rs. 7.46 crore for the previous year.
The provision for taxation during the year is Rs. 311 crore as compared to
Rs. 58 crore last year. The increase is on account of hike in book profit
to Rs. 1376 crore as against Rs. 416 crore in the previous year. Presently,
the Company is being subjected to Minimum Alternate Tax @ 19.93% including
surcharge and cess on tax after availing tax holiday benefits available
under provisions of the Income Tax Act, 1961.
The amount received towards interest on Research & Development Fund,
Renovation & Modernization Fund and Decommissioning levy with interest
thereon has not been considered as income of the Company. These funds are
held by NPCIL on behalf of the DAE and the Decommissioning levy is
collected from beneficiaries based on a statutory notification issued by
the DAE. The Income Tax Tribunal has decided that the interest earned on
these funds be treated as income of the Company. While an appeal has been
filed in the Honorable High Court of Maharashtra, Mumbai, the Company has
appropriated Rs. 27 crore from these funds towards the income tax, if
finally, payable on these levies.
The Company has been able to regulate its operational efficiency and has
been able to achieve a net profit of Rs. 1376 crore after tax.
The accumulated net deferred tax liability as on 31st March 2011 was Rs.
1893 crore on account of timing differences between book and tax profits.
Since Income tax payable on income from generation of power is recoverable
from the beneficiaries, the amount of deferred tax, so recognized, is
recoverable on becoming a part of the current tax.
Therefore, such deferred tax is considered as recoverable and netted from
such deferred tax liability / expense.
CAPITAL:
There was no addition to the paid up share capital during the year. The
Company has not drawn any budgetary support from the Government of India
since FY 2004-05. The total equity paid-up capital continued to be Rs.
10145 crore as on 31st March 2011 against the Authorized Capital of Rs.
15000 crore.
DIVIDEND:
The Board has recommended a final dividend @ 30% of Profit After Tax (PAT)
of the Company. This amounts to Rs. 412.90 crore, including the interim
dividend of Rs. 150 crore.
RESOURCE MOBILISATION:
As per the plan of allocation approved by the Government of India, the
Company raised a sum of Rs. 3000 crore during the year for its various
projects by resorting to market borrowing by availing term loans from
Public Sector Banks. The Company has redeemed Bonds of Rs. 148 crore during
the year, as per the terms of their issue.
OPERATING PERFORMANCE OF THE STATIONS:
The performance of all operating stations was satisfactory during the year
2010-11 and these generated 26472 MUs of electricity (exclusive of infirm
generation of 1 MU from Kaiga-4) recording the highest nuclear power
generation since the incorporation of the Company. The overall Capacity
Factor (i.e. Plant Load Factor) was 71% and the weighted average
Availability Factor was 89%. In addition, Kudankulam Wind Farm generation
during the year was 23 MUs.
MAJOR HIGHLIGHTS:
* Kaiga-4 attained first criticality on 27th November 2010 was synchronized
to the grid on 19th January 2011. The Unit commenced commercial operation
on 20th January 2011.
* For the first time, NPCIL total operating power on a day crossed 4282 MW.
* Generation of over 100 MUs of electricity in a single day on 20th
February 2011.
* After successful completion of Renovation & Modernization activities viz.
EMCCR, EMFR together with upgrades, NAPS-2 and KAPS-1 were synchronized to
the grid on 6th September 2010 and 12th January 2011 respectively. These
activities were carried out with indigenously developed technology. India
is one of the few countries in the world having expertise in Life
Management of PHWRs.
* During the financial year, more than 90% Availability Factor was recorded
by TAPS-2, TAPS-3, RAPS-2, RAPS-4, MAPS-1, NAPS-1, KAPS-1, KGS-1 and KGS-3.
* The uninterrupted continuous runs were as follows:
Reactor No of days From To
TAPS-2 590 22.07.2009 03.03.2011
MAPS-2 432 25.01.2009 03.04.2010
KAPS-2 406 04.07.2009 14.08.2010
RAPS-3 404 26.06.2009 05.08.2010
MAPS-1 346 17.12.2009 28.12.2010
* Calandria vault water leakage at KAPS-1 reactor was successfully repaired
using innovatively designed remote welding technique.
* KAPS-1&2 were placed under International Atomic Energy Agency (IAEA)
Safeguards and operated at full power.
HIGHLIGHTS OF THE OPERATING PERFORMANCE OF THE STATIONS:
The commercial generation, the yearly Capacity Factor (CF) and the annual
Availability Factor (AF) are summarized in the Table.
Station: A B C D E
taps 1 160 1142 81 82
2 160 1274 91 92
3 540 3582 76 93
4 540 3124 66 88
Station Total 1400 9122 74 90
raps 2 200 1720 98 94
3 220 1564 81 85
4 220 1807 94 96
5 220 1753 91 89
6 220 1060 55 59
Station Total 1080 7904 84 84
maps 1 220 1260 65 98
2 220 979 51 85
Station Total 440 2239 58 92
naps 1 220 1228 64 94
2 220 658 61 90
Station Total 440 1886 63 93
kaps 1 220 370 89 92
2 220 1076 56 86
Station Total 440 1446 62 86
kgs 1 220 1260 65 97
2 220 988 51 77
3 220 1334 69 96
4 220 293 78 84
Station Total 880 3875 63 90
NPCIL TOTAL 4680 26472 71 89
A = Unit No.
B = Capacity (MW)
C = Generation (MUs)
D = CF (%)
E = AF (%)
Note:
NAPS-2 and KAPS-1 after capital maintenance were synchronized to the grid
on 6th September 2010 a 12th January 2011.
KGS-4 commenced commercial operation on 20th January 2011.
FUEL AVAILABILITY:
The use of imported fuel for reactors placed under IAEA Safeguards and
increased supply from indigenous sources resulted in operation of reactors
at higher capacity factors. The power level of three PHWRs (TAPS-3&4 and
Kaiga-4) was raised during the year. Other PHWRs were operated at reduced
power level of about 70% consistent with fuel availability.
COMPLETED PROJECTS:
Kaiga Atomic Power Project-4 (220 MW PHWR):
Kaiga-4 attained first criticality on 27th November 2010 after the fuel was
made available during the year 2010-11. The unit commenced commercial
operation on 20th January 2011
ONGOING PROJECTS:
Kudankulam Nuclear Power Project-1&2 (2x1000 MW VVERs):
The 2x1000 MW Kudankulam Project, located in Tirunelveli district of Tamil
Nadu, is being implemented with technical cooperation from Russian
Federation within the framework of the Inter-Governmental Agreement between
India and the Russian Federation. All the equipment and the construction
drawings are being supplied by the Russian Federation while civil
construction, erection of equipment and commissioning of the systems are
being executed by NPCIL. The construction of the project commenced on 31st
March 2002 with the first pour of concrete.
The project has recorded a cumulative progress of 96% as of March 2011
(Unit-1: 98% and Unit-2: 93%) with cumulative expenditure of Rs. 13781
crore. The break-up of progress achieved is: Design & Engineering 99% and
Procurement & Supplies 99%. The Construction & Erection activities for
Unit-1 are complete and in respect of Unit-2, all the civil construction
work is complete and erection works are in advanced stage of completion.
For Unit-1 of the project, significant milestones on the commissioning
front were achieved during the year. These are completion of 'Hydro Test
(Strength Test) of Primary Circuit at 24.5 MPa of the Nuclear Steam Supply
System and Secondary Circuit at 10.8 MPa' and 'Strength and Leak Rate Test
of Reactor Building Containment'. The preliminary works for carrying out
the 'hot run' test at designed parameters are completed.
Erection works for Unit-2 are closely following those of Unit-1. All the
civil construction works have been completed and erection works are in
advanced stage of completion. Trial assembly of the reactor pressure vessel
and the reactor internals has been completed. The main fuel pool was fill-
tested with de-mineralized water for carrying out the liner integrity
checks. Turbine and generator erection has been completed and turbines are
boxed up. Cabling works for loads in various buildings is in progress.
NEW PROJECTS uNDER CONSTRuCTION:
Kakrapar Atomic Power Project-3&4 (KAPP-3&4):
The construction of KAPP-3&4 took off by laying the First Pour of Concrete
on 22nd November 2010 after receiving regulatory clearances. KAPP-3&4 is
the first twin reactor of 700 MW series being launched by NPCIL.
Since first pour of concrete, various project activities are being executed
expeditiously. Works are being executed simultaneously for all main plant
buildings. The infrastructure facilities both at Plant Site and Colony are
being established in line with the project requirement.
KAPP-3&4 are slated for completion in the year 2016.:
Rajasthan Atomic Power Project-7&8 (RAPP-7&8):
The excavation work for two indigenously designed 700 MW PHWRs at RAPP-7&8
has commenced on 19th August 2010 after receiving regulatory clearances
from the Atomic Energy Regulatory Board. Earlier, the contract for Main
Plant Civil Works was awarded.:
The excavation of Reactor Buildings has been completed and the regulatory
clearance for First Pour of Concrete for the unit has been received on 16th
July 2011. The FPC was achieved on 18th July 2011.
The orders for all major long delivery items have been placed. The project
is slated for completion in the year 2016.
Kudankulam Nuclear Power Project-3&4 (KKNPP-3&4):
The Kudankulam Project Unit-3&4 is an expansion of Unit-1&2, located in
Tirunelveli district of Tamil Nadu, being implemented with cooperation from
Russian Federation (RF) within the framework of the Inter-Governmental
Agreement signed between RF and India in December 2008.
The Ministry of Environment & Forests (MoEF) has conveyed environmental
clearance. The process for Coastal Regulation Zone clearance from MoEF is
in progress. Siting consent has been obtained from AERB. The application
for excavation consent has been made to AERB.
Techno-commercial discussions in respect of 2 x 1000 MW VVERs at KKNPP-3&4
with Atomstroyexport, Russian Federation are in the advanced stages of
finalization.
A contract for the first priority design works for initial design
activities has been signed with Atomstroyexport and the work is in
progress. The various pre-project activities were also completed.
Jaitapur Nuclear Power Project (JNPP):
The land measuring 938 Ha was acquired and handed over to NPCIL by the
District Administration, Ratnagiri, Maharashtra. Agreement for
Rehabilitation of Project Affected Families of JNPP has been signed between
NPCIL and Government of Maharashtra.
The Ministry of Environment & Forests, Government of India, has conveyed
environment as well as CRZ clearance for 6 x 1650 units for JNPP.
The General Framework Agreement and Early Work Agreement have been signed
between NPCIL and AREVA, France for implementation of EPR at Jaitapur Site.
Techno-commercial discussions with AREVA in respect of 2 x 1650 MW EPR
units at Jaitapur Site are in advanced stage of conclusion.
Pre-project activities viz. Geo-technical investigations, Construction of
property-cum-boundary wall of Plant Site and Master Plan for residential
complex are in progress.
PROJECTS AT NEW SITES:
In 2009, the Government of India has given 'In-principle' approval for full
potential of Sites at Kudankulam and Jaitapur and also for five new sites;
two for indigenous PHWRs and three for LWRs based on foreign cooperation.
The details of the 'In-principle' approval / full potential are
Capacity
Location Reactor Type (MW)
1. Haryana Indigenous 4 x 700
2. Madhya Pradesh PHWRs 2 x 700
3. Kudankulam, Tamil Nadu 4 x 1000
4. Jaitapur, Maharashtra LWRs 6 x 1650
5. Mithi Virdi, Gujarat based on 6 x 1000
6. Kowada, Andhra Pradesh International 6 x 1000
7. Haripur, West Bengal co-operation 6 x 1000
Jaitapur and five sites located in Haryana, Madhya Pradesh, Gujarat, Andhra
Pradesh and West Bengal as mentioned above are greenfield sites.
The pre-project activities at new sites are in progress. These include
opening of the NPCIL offices in nearby towns, Environment Impact Assessment
for MoEF clearance, design input for regulatory clearance, steps for
obtaining siting consent from the regulator, public awareness programmes
and actions for land acquisition to prepare the sites ready for project
construction within shortest time.
The land acquisition applications for issuance of Section 4 notification
under Land Acquisition Act, 1894 have been already submitted to the
respective District Authorities in Haryana, Gujarat, Madhya Pradesh and
Andhra Pradesh. In case of Haryana, the notification under section 4 was
issued and the objections received under section 5A under the said Act were
responded. The Section 6 notification was approved by Haryana Government on
25th July 2011.
NEW INITIATIVES AND BuSINESS DEVELOPMENT
NPCIL is taking various new business initiatives for public-public as well
as public-private partnership to strengthen the Indian Nuclear Power
capability and expanding power generation capacity.
NPCIL with L&T Ltd.
NPCIL and Larsen & Toubro Ltd. set up a Joint Venture Company in the FY
2009-10 under the name 'L&T Special Steel & Heavy Forgings Pvt. Limited'
(LTSHF) as a subsidiary of L&T Ltd. with NPCIL having 26% shareholding.
This Public-Private Partnership will produce special steels and ultra heavy
forgings including those required for Nuclear Power Plants. The
construction work at site is in full swing at Hazira, District Gujarat. It
is expected that trial production of forgings would commence in October
2011.
JV with NTPC Ltd.
NPCIL and NTPC Limited have incorporated a Joint Venture Company under the
name of 'Anushakti Vidhyut Nigam Limited' on 27th January 2011 to set up
Nuclear Power Projects in the country. The JV Company is a subsidiary of
NPCIL with 51% of share capital held by NPCIL.
JV with IOC Ltd.
A Joint Venture Agreement was signed in January 2011 between NPCIL and
Indian Oil Corporation Limited (IOCL), a Government of India Enterprise, to
form a joint venture company to set up Nuclear Power Projects in the
country. The JVC under the name 'NPCIL - Indian Oil Nuclear Energy
Corporation Limited' was incorporated on 6th April 2011 as a subsidiary of
NPCIL.
JV with THDCIL
NPCIL and Tehri Hydro Development Corporation of India Ltd. (THDCIL), have
signed an agreement for preparation of Detailed Project Report (DPR) of the
Pumped Storage Scheme (PSS) having installed capacity of 700 MW at Malshej
Ghat, near Mumbai. The survey and investigations have been completed and
the DPR is submitted to the Government of Maharashtra. The JV partners are
expecting formal award of the project by the Government of Maharashtra.
Joint Venture with other CPSus
MOUs have been signed in the FY 2009-10 between NPCIL and National Aluminum
Company Limited (NALCO) to form Joint Venture Company to work together for
setting up Nuclear Power Plants. The discussions are in progress to form
the JVC.
Renewable Energy Developments
In line with the national priority, NPCIL is also contemplating utilization
of Solar Energy for specific applications such as operating vapour
absorption machine for cooling, desalination and generation of electricity.
Techno-economic viability of the use of Solar Energy for these applications
is planned to be evaluated.
NPCIL has already made a beginning in utilization of Renewable Energy at
KKNPP site where a 10 MW Wind Power Plant is already in operation since
January 2007. NPCIL is considering the installation of additional Wind Farm
at the same location.
ENGINEERING & PROOJREMENT
NPCIL is spearheading the efforts for capacity add-ons following indigenous
route of proven PHWR technology which has been well adapted and mastered.
3-D modeling of the plant has been done for the first time in NPCIL so as
to issue drawings after ascertaining virtual constructability. Bill of
Materials (BOM) generated thereon also has high level of accuracy and thus
it has been possible to arrive at the material requirement for the project
more precisely. Better definition of scope of work contracts and minimizing
changes during construction will result in improved cost and schedule
performance.
Open bidding has been the guiding principle of NPCIL to encourage wide
participation and competition among the bidders. Proprietary purchases have
been further reduced and brought to the minimal. New General Conditions of
Contract adopted by the Corporation have formed the basis of tendering
process. Total transparency has been brought in tender notification,
qualifying criteria of bidders and bids evaluation methodology.
Purchase Orders for long delivery items are already placed for ongoing
projects. Manufacturing of critical equipment like Steam Generators, End
Shields, Calandria, Reactor Headers, Coolant Channels, Reactivity devices,
Primary Coolant Pumps & Motors, Fuelling Machine Heads and Fuelling Machine
Column & Bridge for eight units have already begun. A strategic
breakthrough was made into forging an alliance with BHEL & GEC Alstom for
the supply of Turbine & Generator for 700 MW Units of KAPP-3&4. Purchase
Order for Plant Water Package has already been placed and field works are
in progress. Critical packages of Nuclear Piping, Common Services Piping,
Balance of Turbine Island works and C&I packages are in different stages of
awarding process.
The Engineering Directorate is also working on the export model for the
single unit plant of 220 MW and 540 MW PHWR reactors.
CONTRACTS & MATERIALS MANAGEMENT
During the year, the focus has been to process the requirements of upcoming
700 MW projects viz. KAPP-3&4 and RAPP-7&8. Placement of purchase orders in
respect of long delivery equipment / items were made in a timely manner to
meet the project schedule.
NPCIL has innovatively implemented and successfully operated Integrated
Materials Management and achieved substantial cost benefit.
REACTOR SAFETY AND ANALYSIS
The Directorate of Reactor Safety & Analysis (RSA) is responsible for carrying out the safety assessment for Nuclear Power Plants right from design, siting, commissioning and safe operation. It completed the Preliminary Safety Analysis Report (PSAR) of the 700 MW units meeting First Pour of Concrete requirements for KAPP-3&4 and RAPP-7&8 and performed comprehensive large break Loss of Coolant Accident (LOCA) analysis including identification of critical break, considering interleaved feeders configuration, 3D-neutron kinetics and limited boiling in the channels with several first of a kind features. The analysis demonstrated adequacy of safety systems and availability of large safety margins for KAPP-3&4.
An innovative decision making tool namely Symptom based Intervention Guidelines Management System (SIGMAS) has been implemented in RAPS-5&6 as an operation aid to handle emergency conditions. Safety Analysis for Hydrogen Management in Containment during Severe Accident along with SIGMAS was carried out. NPCIL participated in the IAEA Coordinated Research Project on benchmarking of severe accident analysis codes for Heavy Water Reactors.
First of its kind activities covering internal flood Probabilistic Safety Assessment (PSA), Fire PSA for KAPS-1&2 and Level-1 PSA for internal events has been completed for
RAPS-2.
HEALTH, SAFETY AND ENVIRONMENT
Nuclear Power Plants (NPPs) of the Company have registered more than 335
reactor years of safe, reliable and accident-free operation.
NPCIL accords utmost importance to nuclear, radiological, industrial, fire
and environmental safety, over-riding the demands of production or project
schedules. Continuing with its policy of 'Safety First' and striving for
maintaining the highest standards of safety within NPPs, the occupational
exposures of employees of the Company at various NPPs were maintained well
below the values specified by the regulator, Atomic Energy Regulatory Board
(AERB). Continuing with the emphasis on the principle of ALARA (As Low As
Reasonably Achievable), the yearly radiation dose around the NPPs, measured
over the last many years, is an insignificantly small fraction of natural
radiation dose and the stipulated regulatory limits.
For ensuring effective safety culture, different levels of reviews are in
place to bring excellence in safety performance such as review by
Directorate of Health, Safety & Environment, peer review by international
agency, corporate review by a team of senior officers from stations &
headquarters, Internal Review / Self Assessment by station and regulatory
review by regulatory body. In line with the commitment of practicing the
international safety standards, TAPS-1&2 was offered for peer review which
was conducted by World Association of Nuclear Operators (WANO). During the
year, the Corporate Review was carried out for TAPS-1&2, TAPS-3&4, RAPS-
1&2, RAPS-3&4, NAPS, KAPS and KKNPP. The Internal Reviews / Self
Assessments were undertaken by Stations for assessment and reinforcement of
safety practices and safety culture.
Operational Health Physics functions at all NPPs were performed
prioritizing the safety. The radiological safety aspects of PSAR of KAPS-
3&4 (700 MW) and RAPS-7&8 (700 MW) were prepared. Various technical
assignments for general plant requirements of JNPP were reviewed and
finalized. Review of post closure safety assessment of Near Surface
Disposal Facility (NSDF), KAPS was carried out.
The Environmental Management System (EMS) and Occupational Health and
Safety Management System (OHSMS), as per ISO-14001:2004 and IS-18001:2007
respectively, were maintained at all the stations. An Environment
Management Meet - 2010 was organized at NPCIL HQ focusing on environmental
legislative compliances and effective maintenance of environmental
management system.
Continual strengthening of Industrial and Fire Safety activities at
stations and projects remained the main focus during 2010-11 as well.
Strengthening of safety organization and manpower planning up to 2018 was
carried out. A safety guide on Construction Safety Management was also
brought out in this direction. Implementation of Behavior Based Safety
(BBS) programmes was given thrust. Celebration of National Safety Day with
numerous awareness programmes carried significant importance for safety
propagation. Independent review cum exchange visits to projects, self
assessment of stations and corporate reviews were taken up as review
techniques, for strengthening Industrial and Fire Safety.
Nuclear Safety:
Safety has always been NPCIL's continuous endeavor. In pursuit of safety
improvements, it carries out comprehensive and systematic safety
assessments by multi-tier multi-disciplinary review system during design,
construction, commissioning and operation of NPPs. The assessments are well
documented, subsequently updated (in the light of operating experience and
significant new safety information) and reviewed at station level and
corporate level and subsequently by the regulatory body. Verification by
analysis, surveillance, testing and inspection is carried out to ensure
that the physical state and the operation of a nuclear installation
continue to be in accordance with its design, applicable national safety
requirements and operational limits and conditions.
Every event in an operating NPP is reviewed and lessons are learnt. The
internationally reported events and their applicability to Indian NPPs are
checked. Analysis of events is done to establish their root cause and
accordingly the systems, procedures, aspects related to training and safety
culture are further improved. These mechanisms have resulted in progressive
improvements in the safety and reliability of units over the years. The
inputs from operational experience are utilized for design improvements in
the new reactors. Self assessment at sectional level, station level and
corporate level are routinely organized to assess safety culture from an
individual's perspective to the Company's goals on this issue. The targets
are reviewed regularly to ensure that they continue to promote improvement.
Peer reviews services by WANO are effectively utilized to gain safety
assessment and insights on international level and avoid insular thinking
on safety matters and broadening the range of 'operational feedback'.
Recently, after the nuclear incident at Japan's Fukushima NPP which was
triggered by Tsunami, NPCIL proactively constituted four task forces, one
each for different generations of reactor design, which have reviewed
preparedness and recommended measures for the 'beyond design basis
scenarios'. All Stations have reviewed the status at the station with
reference to the recommendations forwarded by WANO in this regard. Detailed
walk-down of all the plants have also been conducted by specially
constituted teams for this purpose. In the same context, two additional
task forces reviewed the plants under construction - the Kudankulam units
and the 700 MW units.
QUALITY ASSURANCE:
NPCIL, in all its endeavors, is committed towards upgradation and
continuous improvement in Quality Management, Quality Assurance /
Surveillance, Pre-service Inspection / In-service Inspection and interface
with regulatory body. Quality Assurance / Surveillance activities have been
carried out expeditiously for Projects and Stations. QA Directorate has
ensured timely and effective QS coverage to meet the Projects and Stations
schedules.
Review and revision of In-service inspection programme document of TAPS-1&2
and MAPS-1&2 were undertaken. Developmental activities related to NDE
tooling required for performing In-service Inspection has been undertaken.
As part of indigenization, manipulator based Eddy Current Testing System
has been developed for Steam Generator tubes of LWR and PHWR.
Corporate QA reviews of Projects and Stations (including PSI / ISI audits)
have been completed in a planned way. QA reviews have been conducted based
on WANO guidelines.
Emphasis was given for training and certification of QA manpower. In-house
NDE training has also been imparted to QA Engineers and Scientific
Assistants. Strengthening of QA activities has been undertaken by effective
implementation of ISO-9001, imparting training and certification.
Technical assistance and expediting of various Nuclear Power Plant
components orders placed by PFBR Project (BHAVINI) and KKNPP have been
provided by QA Directorate during the year.
NPCIL continued to provide QA consultancy services to BARC, BHAVINI, DRDO,
ITER-India and various State Electricity Boards in the country.
HUMAN RESOURCE MANAGEMENT
Human resource is the most vital asset of the organization and its
performance has been improving year after year due to investment in
enhancement of knowledge through training and skill development. A detailed
projection of human resource management is made in the Management &
Discussion Analysis which is annexed as Annexure-B to the Report.
Implementation of Reservation Policies.
SC/ST/OBC reservation policies are being fully complied with and
development of SC / ST personnel is being given paramount importance.
Reservation has also been provided to physically challenged as per rules /
policy. Presently, 84 physically challenged persons are on rolls of NPCIL.
The following represents the statistical information on reservation and
related matters:
Strength of reserved categories as on 31st March 2011.
Total No. of
Group Employees SC ST OBC
A 4065 310 69 401
B 4468 716 277 796
C 3301 747 346 927
TOTAL 11834 1773 692 2124
Promotions effected during the year 2010-11.
Total No. of
Group Promotions SC ST OBC
A 601 45 12 62
B 590 111 37 123
C 580 160 38 133
TOTAL 1771 316 87 318
IMPLEMENTATION OF OFFICIAL LANGuAGE
NPCIL fully complies with the Government of India directives on
implementation of Rajbhasha, 'Hindi'. NPCIL has been relentlessly making
all efforts towards continuous improvements in the progressive use of
official language among all its units, projects and HQs. NPCIL's efforts in
propagation of official language have been receiving commendations and
awards at various fora.
Awards and Recognitions for implementation of Official Language:
* NPCIL was awarded first prize for the year 2009-10 for best performance
in the field of Official Language Implementation by a non-government Social
and Literary Organization 'Ashirvaad' working for propagation and promotion
of Hindi language since 40 years in Mumbai, Maharashtra.
* NPCIL was awarded third prize for excellent performance in the field of
Official Language Implementation by Town Official Language Implementation
Committee, Mumbai for the year 2009-10 under the category of large Public
Sector Undertakings (PSUs).
To encourage the officers / employees of NPCIL to do their official work in
Hindi and allay their apprehensions regarding use of the language, 32
workshops were organized during the year and 823 officers / employees were
trained in these workshops.
During the period, total 96 Hindi monthly competitions were conducted to
promote the use of official language which were attended by more than 2769
participants.
In continuation of the efforts, an 'All India Hasya Kavi Sammelan' was
organized on the occasion of Vishva Hindi Divas on 10th January 2011.
The Parliamentary Committee on Official Language carried out inspection of
QA Office, Noida on 8th June 2010 and Tarapur Maharashtra Site on 4th
January 2011 to evaluate NPCIL's endeavor in the field of Official Language
Implementation. The Official Language related work being done at NPCIL was
appreciated by the Committee during these inspections.
VIGILANCE
Vigilance is an important parameter of good corporate governance. The prime
objective of Vigilance is to eradicate corruption and malpractices in the
organization. The Vigilance Directorate has been playing an important role
in imparting knowledge and enhancing awareness by sensitizing employees
towards this direction. The focus is to encourage the system improvements
to increase efficiency and productivity. The use of website developed by
Vigilance Directorate hosts the guidelines issued by Chief Vigilance
Commission (CVC) / NPCIL as a tool of communication for remaining vigilant.
* A book on 'Preventive Vigilance for Purchase Contracts' was published to
enhance efficiency and effectiveness of scientific officers and managers in
Contract Management.
* A number of System Improvements concerning Contract management, IT
working, Finance and Personnel matters were implemented.
* To boost preventive vigilance and to spread vigilance awareness, 9 one
day seminars were organized at Headquarters and Units. Experts from Central
Vigilance Commission and other eminent speakers from outside organizations
were invited to address the seminars.
* A documentary film titled 'Bhabha's Vision - Our Mission' containing
vigilance message was produced in-house to motivate young scientific
officers and other employees in the organization. Apart from the progress
made by NPCIL, the film highlights the path shown by Dr. Bhabha with
reference to Transparency, Integrity and Dedication towards peaceful use of
nuclear energy.
* First-ever Hindi Song on Vigilance i.e. 'Satarkta Abhiyan' was written
and composed through in-house efforts.
* Vigilance Awareness Period was observed in NPCIL Headquarters and all the
Units during the period 25th October to 1st November 2010. CHETNA - annual
edition of Vigilance Magazine was released during Vigilance Awareness
Period.
* NPCIL hosted a meeting of Vigilance Study Circle, Mumbai Chapter in
December, 2010.
* CVO and Vigilance Officers carried out 117 inspections including surprise
inspections of ongoing contract works. Two CTE type examinations were also
conducted, apart from other investigations.
E-GOVERNANCE
NPCIL is committed to the fulfillment of the expectations of stakeholders
through continued enhancement of effectiveness, efficiency and transparency
in its functions. In order to meet the above objective, potential of
Information Technology as an enabler in its pursuit to achieve operational
excellence is being leveraged.
Over the years, NPCIL has employed Information Technology (IT) to automate
work processes in order to build robust and transparent systems, improve
efficiency, maintain records easing the day to day work of its around 12000
strong parivar. IT has endeavored to support automation of all the wings of
NPCIL viz. HR, Finance, Purchase, Inventory, Operations and Maintenance.
Major IT endeavors include the following:
* Corporate Human Asset Review and Management System (CHARMS).
* Computerised Maintenance Management System (CMMS).
* Computerised Event Reporting System (CERS).
* Integrated Business Application (IBA).
* Annual Performance Assessment Report (e-APAR).
CORPORATE SOCIAL RESPONSIBILITY
NPCIL being responsible corporate citizen is committed for the philosophy
of caring and sharing. NPCIL has always been well aware of the need to
benefit society by enhancing the quality of lives of people in and around
its power plants and surrounding areas. The organization continues to play
an active role through a host of community development initiatives. The
focus was on healthcare, education, infrastructure development and
environment.
In order to strengthen further the benefits to society by enhancing the
lives of people around its power plants and surrounding areas management
began a strong initiative to constitute a dedicated group headed by an
official in the rank of Executive Director. The group was entrusted with
the responsibilities for Rehabilitation and Resettlements for new Projects
as well as the policy formulation, planning, developing the system of
implementation and monitoring the Projects and activities pertaining to
Corporate Social Responsibilities (CSR) for operating nuclear power
stations and projects of NPCIL as well as initial community development
near new projects.
A comprehensive guideline on Corporate Social Responsibility in line with
guidelines issued by Department of Public Enterprises has been put in place
for clear direction for planning, implementation and monitoring of the
same.
An Advisory Council with eminent members having wide experience has been
formed as an Apex body to guide and advice on matters pertaining to CSR and
R&R.
Rs. 8 crore was sanctioned for implementation of CSR works by all the
operating sites and projects during 2010-2011. Out of this, Rs. 6 crore was
spent or committed to be spent against total 77 activities/projects.
In the past CSR activities were taken up based on the experience and the
specific requirement of the surrounding areas around operating stations.
More structured programme for sustainability and reaching the benefits to
the community has been chalked out.
NPCIL continues to focus on three major key dimensions like health,
education and infrastructural support for overall development of the
villages around Nuclear Power Plants.
CORPORATE ENVIRONMENTAL RESPONSIBILITY
NPCIL, as a responsible public sector enterprise, is conscious about its
Corporate Responsibility towards Environment. The 'Environment Safety' has
been prominently included in its Mission Statement and is also reflected in
the HSE Policy Statement. There is a functional group established at HQ for
oversight and guidance on Environmental Safety. The stations and projects
are pursuing the Environmental Goals and Objectives of NPCIL. Operating
stations have also adopted Environment Management Systems, in line with
ISO-14001, and are audited and certified periodically by the accredited
agencies. The Environment Management Meets are organized to propagate the
knowledge and requirements of Environmental Safety and share Good Practices
in this regard.
CORPORATE COMMUNICATION
To enhance the information to stakeholders external and internal
communication initiatives were augmented. Periodically, the achievements of
NPCIL were highlighted through print and electronic media throughout the
country. NPCIL website was strengthened by loading large public information
material essentially to raise awareness on nuclear power, safety of nuclear
power, radiation aspects and so on. Several publications in different
languages on Jaitapur Nuclear Power Project (JNPP) are also released.
A Hall of Nuclear Power at Nehru Science Centre, Worli, Mumbai was also
commissioned to share factual information on nuclear energy, nuclear power
plants, health, radiation and safety among the visitors from various target
groups. This hall of nuclear power comprises of interactive models,
information kiosks, displays on all facets of nuclear power.
An information centre comprising of multimedia kiosks, back-lit and front-
lit panels and other interactive exhibits have been commissioned at the
corporate office in Mumbai, especially to share key information regarding
NPCIL and nuclear power to the visitors and employees.
The Company organized several awareness campaigns on nuclear power and
NPCIL including safety aspects, site selection process and pre-project
activities. The awareness programmes were also conducted for the
surrounding population, student and teacher community, revenue officers and
journalists around the new green-field sites. The Company also organized
scientific and technical displays at ten exhibitions showcasing the
Company's achievements, capabilities and the benefits of nuclear power. In
addition, exclusive exhibitions in Marathi language were organized in
respect of JNPP at Mumbai and Ratnagiri region essentially to share the
information on nuclear power, JNPP and allay the apprehensions of public.
THE RIGHT TO INFORMATION ACT, 2005
An elaborate mechanism exists with 7 Nos. of Assistant Public Information
Officers, one at each site, one Central Public Information Officer and an
Appellate Authority at Headquarters to deal with the requests received
under the RTI Act.
CPIO's Office has been established with adequate manpower to carry out its
functions. The mandatory information required under the Act [section
4(1)(b)] has been posted on NPCIL website and the information was updated
as required.
Three Hundred and Eighty Two (382) requests were received during the year
2010-11 under RTI Act, 2005, which have been replied. Sixty two (62)
numbers of first appeals were disposed off.
PARTICIPATION IN INTERNATIONAL ACTIVITIES
NPCIL continues to be a member of various international organizations viz.
World Association of Nuclear Operators (WANO), CANDU Owners Group (COG) and
World Association of Nuclear Association (WNA). NPCIL actively participated
in various programmes of these organizations to enhance the safety and
reliability of its nuclear power plants.
NPCIL also participates in various International Atomic Energy Agency
(IAEA) and Nuclear Energy Agency (NEA) activities. NPCIL participated in
preparation and presentation of National Report for International
Convention on Nuclear Safety at IAEA, Vienna.
NPCIL is one of the first members of WANO and is currently member of two
WANO regional centres at Tokyo and Moscow. All the nuclear power plants
operating in over 30 countries of the world are its members. Dr. S.K. Jain,
Chairman & Managing Director is on worldwide WANO governing board.
During the current year, NPCIL hosted WANO Peer Review of its plants which
were carried out by teams consisting of experts from several countries
representing global nuclear safety standards and found to be very useful in
bringing in international perspective to our plants. Also, WANO organized
Technical Support Missions for NPCIL to achieve next higher level of safety
and reliability. Several persons from NPCIL participated in the important
meetings, seminars and peer reviews organized by WANO and had the
opportunity to discuss various issues related to improvement in plant
performance with experts from other countries.
COG has installed a satellite server to replicate all the data available of
main server of COG for easy and fast access to valuable data available on
COG. The database has also been provided access to plant sites so that they
remain connected with latest developments in safety of operating CANDU
plants worldwide. NPCIL participants regularly participate in various
programmes.
NPCIL also draws benefit from membership of WNA; especially it provides
detailed worldwide report on all related issues of fuel like availability,
utilization and forecast for future.
Recently NPCIL got significantly benefitted from above organizations in
obtaining accurate and timely information on Fukushima accident in Japan.
DIRECTORS' RESPONSIBILITY STATEMENT
As required under Section 217(2AA) of the Companies Act, 1956, the
Directors confirm:
1. that in the preparation of the annual accounts, the applicable
accounting standards have been followed, along with proper explanation
relating to material departures;
2. that they have selected such accounting policies and applied them
consistently and made judgments and estimates that are reasonable and
prudent so as to give a true and fair view of the state of affairs of the
Company at the end of the financial year and of the profit or loss of the
Company for that period;
3. that they have taken proper and sufficient care for the maintenance of
adequate accounting records, in accordance with the provisions of the
Companies Act, 1956 for safeguarding the assets of the Company and for
preventing and detecting fraud and other irregularities;
4. that they had prepared the annual accounts on a going concern basis.
CONSERVATION OF ENERGY / TECHNOLOGY ABSORPTION / FOREIGN EXCHANGE EARNINGS
AND OuTGO
Particulars as required under Section 217(1) (e) of the Companies Act, 1956
read with the Companies (Disclosure of Particulars in the Report of the
Board of Directors) Rules, 1988, are given in Annexure-A to this report.
PARTICuLARS OF EMPLOYEES
Pursuant to Section 217(2A) of the Companies Act, 1956 read with the
Companies (Particulars of Employees) Rules, 1975 as amended, none of the
employees of the Company were in receipt of remuneration in excess of
limits prescribed under the said rules.
MANAGEMENT DISCUSSION AND ANALYSIS
Annexed as Annexure-B to this report.
CORPORATE GOVERNANCE
The Department of Public Enterprises (DPE) has laid down guidelines on
Corporate Governance for CPSEs. The Department of Atomic Energy (DAE), the
administrative ministry of NPCIL, has requested NPCIL to comply with the
instructions. The guidelines are similar to the Corporate Governance Clause
in the Standard Listing Agreement of Stock Exchanges.
The Board members and senior management have reaffirmed the compliance with
the code of conduct.
A compliance report on Corporate Governance is given as Annexure-C.
The Company has obtained a certificate from M/s. Parikh & Associates, a
firm of Practicing Company Secretaries regarding compliance of conditions
of corporate governance as indicated in the DPE Guidelines. The Compliance
Certificate is annexed to this report as Annexure-D.
STATUTORY AUDITORS
The Statutory Auditors of your Company are appointed by the Comptroller &
Auditor General of India. M/s. Kalani & Co., Chartered Accountants, Jaipur
were appointed as Statutory Auditors for the Financial Year 2010-11.
OBSERVATIONS OF THE STATUTORY AUDITORS
Comments of the management on the observations of the Statutory Auditors
are given in Annexure-E to the report.
COMMENTS OF THE COMPTROLLER AND AUDITOR GENERAL OF INDIA
The accounts for the year ended 31st March 2011 were reviewed by the
Comptroller and Auditor General (C&AG) of India. Comments of the C&AG on
annual accounts have been given as Annexure to the report.
CHANGES IN THE BOARD OF DIRECTORS
* Dr. Srikumar Banerjee, who has been appointed as Chairman, Atomic Energy
Commission and Secretary, DAE, has relinquished charge of the post of
Director, BARC w.e.f. 19th May 2010 and consequently ceased to be Director
of NPCIL.
* Shri H.L. Bajaj, Member (Technical), Appellate Tribunal of Electricity,
who had been re-appointed as a part-time Director on 16th December 2008,
ceased to be Director w.e.f. 19th May 2010 upon his attaining the age of 65
years.
* Dr. Nalini Bhat, Adviser (IA), Ministry of Environment & Forests has been
appointed as a part-time Director on the Board w.e.f. 15th July 2010 vice
Dr. G.K. Pandey.
* Shri V.M. Kaul, Director (Personnel), Power Grid Corporation of India
Ltd. has been appointed as a part-time Director on the Board w.e.f. 15th
July 2010 vice Shri Anand Mohan.
* Shri Chandan Roy, Director (Operations), NTPC Ltd., who had been
appointed as a part-time Director w.e.f. 8th October 2004 ceased to be
Director w.e.f. 1st August 2010 consequent on his superannuation.
* Dr. R.K. Sinha, Director, Bhabha Atomic Research Centre has been
appointed as a part-time director on the Board of NPCIL w.e.f. 15th
September 2010.
* Shri T.S. Bhattacharya, retired Managing Director of the State Bank of
India, who had been appointed as a part-time Director w.e.f. 8th May 2008
for a period of 3 years, ceased to be Director w.e.f. 8th May 2011 on
completion of his term.
* Shri Rakesh Nath, Member (Technical), Appellate Tribunal for Electricity,
has been appointed as a part-time Director w.e.f. 26th April 2011.
* Dr. Arbind Prasad, Senior Adviser (Power & Energy), Planning Commission,
has been appointed as a part-time Director on the Board w.e.f. 17th June
2011 vice Shri S.P. Sethi.
* Shri J.K. Ghai, Director (Finance), NPCIL who had been appointed as a
whole-time Director since 10th February 2006, ceased to be Director on
completion of his term on 31st July 2011.
The Board welcomes appointment of Dr. Nalini Bhat, Shri V.M. Kaul, Dr. R.K.
Sinha, Shri Rakesh Nath and Dr. Arbind Prasad and places on record its
sincere appreciation of the valuable services rendered by Dr. Srikumar
Banerjee, Shri H.L. Bajaj, Shri Chandan Roy, Shri T.S. Bhattacharya and
Shri J.K. Ghai during their association with the Company.
APPRECIATION
The Board would like to express its gratitude to the Department of Atomic
Energy, Ministry of Power, Ministry of Programme Implementation &
Statistics, Central Electricity Authority, Planning Commission, Ministry of
Environment & Forests, other Ministries, Departments of the Government of
India, State Governments for their cooperation, banks, financial
institutions and other investors who have continued to repose their
confidence in the Company.
The Board would also like to place on record its appreciation of the
services rendered by the auditors for their service and valuable advice.
The Board wishes to express its special appreciation of the hard work put
in by each and every employee of the Company and the cooperation extended
by the Employees' Union, Supervisors' and Officers' Associations.
For and on behalf of the Board of Directors
(S.K. JAIN)
Chairman & Managing Director
Place: Mumbai
Date : 6th August 2011
Annexure 'A' to the Directors' Report
Information under section 217(1)(e) of the Companies Act, 1956 read with
Companies (Disclosure of Particulars in the Report of the Board of
Directors) Rules, 1988 and forming part of the Directors' Report for the
year ended 31st March 2011.
CONSERVATION OF ENERGY
A. Energy Conservation measures taken:
Conservation of energy and optimization of resources have been given high
priority in all the operating Nuclear Power Stations (NPPs) of NPCIL. A
headquarter instruction exists to guide all the stations to take necessary
measures for the conservation of energy. The following energy saving
measures were continued to be taken by the Company.
Energy Conservation Committees which were formed in all the operating NPPs
of NPCIL meet periodically to review the situations and suggest measures
for energy conservation.
Continuous efforts at each station are put in to reduce steam, light water
and compressed air leaks, consumption of various gases viz. hydrogen,
nitrogen, carbon dioxide, helium, etc. and the same is closely monitored.
During station operation, number of running equipment has been optimized.
In some of the stations, particularly in northern region, the benefit of
winter season is fully utilized to operate the units with optimal number of
equipment without any loss of plant efficiency. To reduce the heat losses
from hot piping and equipment, thermal imaging is carried out in all the
stations and remedial measures like repair / replacement of insulation with
better material is done. Equipment modifications and process modifications
in the operating stations were done which resulted in a substantial gain in
consumption of energy.
Continuous trend monitoring of heavy water and light water collections
during reactor operation has helped stations in taking appropriate remedial
measures resulting in reduction in consumption of energy.
During plant shutdown, minimum number of equipment are kept operating for
energy conservation.
Replacement of tube lights/lamps with solar power lamps and energy
efficient lamps, proper maintenance of the vehicles to achieve fuel
efficiency and various other energy conservation measures are taken up on
priority. In off hours lights are optimized in offices, plant area, canteen
and maintenance shops.
14th December 2010 was celebrated as Energy Conservation Day at all our
stations to create awareness towards energy conservation among officers,
employees and their families.
B. Additional investments and proposals for reduction of consumption of
energy:
In all stations use of solar energy has been initiated.
Energy saving lamps are being replaced in place of conventional lighting
fixtures in almost all the stations.
All the stations have targets of their own for next fiscal to bring down
energy consumption in terms of reduction in auxiliary consumption,
replacement of old equipment and lighting fixtures with energy efficient
ones, replacement of conventional fan regulators with electronic
regulators, installation of solar powered lamps and reduction in
consumption of consumables.
C. Impact of measures at A and B above for reduction of energy consumption:
During the financial year, NAPS-2 and KAPS-1 were re-commissioned after
EMCCR and KGS-4 was commission for the first time. Hence, because of
additional requirements for commissioning of these units, the consumptii of
high speed diesel, industrial gases, DM water and TG lub oil was higher as
compared to previous year. Howev the various measures taken by the Stations
for conservation of energy resulted in reduction of Station Auxilia
consumption.
FOREIGN ExCHANGE USED/EARNED (Rs. in crore)
As at As at
31st March 31st March
2011 2010
1. Foreign Exchange Outgo
a) Value of Import based on CIF basis 762 738
b) Expenditure
- Project Related Payments 70 97
- Interest and Agency Fees - -
- Others 5 6
2. Foreign Exchange Earned 0.04 0.10
FORM-B
A. RESEARCH & DEVELOPMENT/TECHNOLOGY DEVELOPMENT (R&D/TD)
1. Specific areas in which R&D/TD is carried out:
R&D/TD activities in the Company are oriented towards addressing the
specific requirements emanating from its operating stations, projects under
construction and the supporting groups within NPCIL. These efforts are
focused more towards continued enhancement of nuclear safety, improvement
in plant performance parameters, reduction in operational costs, reduction
in project gestation period and costs and reduction in Person-Sievert (man-
rem) expenditure. A greater thrust is also being imparted to indigenization
of hitherto imported components and equipment and broadening the vendor
base to facilitate the expansion of nuclear programme.
The efforts are mostly application-oriented design & development
specifically addressing the Control & Instrumentation (C&I) requirements
emanating from power plants under construction and from operating stations
to support the existing C&I electronics systems. The design and development
efforts in R&D-
ES are concentrated towards electronics and computer based controls and
instrumentation systems for 700 MW projects.
Specific areas of development in R&D-ES are standardization of Hardware
Modules, Software building blocks, Human Machine Interface, Generic
Embedded Software, development of computer based C&I systems, interaction
with academic and research institutions to identify future needs for
modernization of C&I, upgradation of computer based systems in operating
stations, etc.
2. Benefits derived as a result of the above R&D/TD:
The establishment of in-house development and testing facilities related to
Nuclear Systems has benefitted the Company in the following areas:
* Performance verification of first of a kind systems related equipment for
700 MW projects such as Containment Spray System, Passive Decay Heat
Removal System.
* Test facilities for nuclear safety studies are established / being
established.
Construction activities of Integral Test Facility at Tarapur (ITFT) and
Hydrogen Recombiner Test Facility (HRTF) have progressed significantly.
* Techniques developed for repair / rehabilitation / refurbishment of
nuclear power plant systems and components.
* Development of Tele-operated manipulators / tools / gadgets for
inspection and maintenance tasks in nuclear power plants.
* Establishment of facility for aging studies and life management of
components.
* Indigenisationofequipment/components. Significant progress has been
achieved in indigenous development of Self-Powered Neutron Detectors
(SPNDs) with requisite confidence to develop a wide range of such detectors
within grasp.
The establishment and maintenance of in-house R&D-ES laboratories and
facilities enabled the Company in the following areas:
* 'Development and Testing of System Software' and 'Finalization of
Hardware' for several Computer Based Systems including safety and safety-
related systems. The validated software was installed and commissioned on
the corresponding hardware panels of the eleven systems at Kaiga-3, Kaiga-
4, RAPS-5 and RAPS-6 and these systems are working satisfactorily.
* Upgradation of Electronics and Computer Based C&I Systems in KGS-1, KGS-
2, RAPS-3 and RAPS-4.
* Development and testing of MCA based Stack Monitoring System and IR based
Annulus Gas Monitoring System and setting up Radiation Monitors Calibration
Test Facility at TAPS R&D Centre.
* Standardization of hardware and software for computer based systems for
new plants which will result in cost savings.
ExPENDITURE ON R&D/TD
a. Capital Rs. 12 crore
b. Recurring Rs. 4 crore
c. Total Rs. 16 crore
d. Total R&D expenditure as % of 0.27%
total turnover
B. TECHNOLOGY ABSORPTION, ADAPTATION & INNOVATION
The Company's self-reliance in the areas of design, construction,
commissioning and operation of Pressurized Heavy Water Reactors (PHWRs) is
near total. Continued efforts are made to upgrade and update the Company's
knowledge-base and to adapt and absorb new technologies that are being
evolved. Boiling Water Reactors (BWRs) are also operated by the Company
meeting international standards on both safety and performance.
Assimilation of technology with respect to the construction of Pressurized
Water Reactors (PWR) and Fast Breeder Reactor (FBR) is also underway.
Innovative techniques have been introduced in reactor design to upgrade 540
MW PHWR to 700 MW by permitting limited boiling in reactor coolant channels
with minimum changes in nuclear components. This has led to relative ease
in review and acceptance by regulatory body of new systems and concepts for
700 MW reactors. It is significant to note that 700 MW design has
essentially conceptualized and incorporated the passive systems and hook-up
schemes which have become relevant post-Fukushima. R&D activities had
included testing and verification of such a new system. The role of
erstwhile R&D Nuclear Systems Group has been expanded and this group is now
known as Technology Development Group. Role of R&D-Electronics Systems
Group is redefined to put greater thrust on development of all safety
related C&I systems with the goals of higher reliability, availability and
cost reduction and to fulfill all requirements of AERB.
Annexure - B to Directors' Report
MANAGEMENT DISCUSSION AND ANALYSIS
ECONOMIC ENVIRONMENT
The Indian economy has emerged with remarkable rapidity from the slowdown
caused by the global financial crisis of 2007-09. GDP grew by 8.6% in FY
2010-11 from 6.8% in FY 2008-09 and 8.0% in FY 2009-10. Growth is strong in
2010-11 with a rebound in agriculture and continued momentum in
manufacturing sector.
INDUSTRY OVERVIEW
India is the world's 5th largest energy consumer in the world and is
expected to become the 3rd largest energy consumer by 2020 (after USA and
China).
India's Power Sector
The Eleventh Five Year Plan (2007-12) originally envisaged a capacity
addition of 78700 MW. The revised Mid Term Appraisal (MTA) target for total
capacity addition is now 62,374 MW, which is lower than the original target
but is nevertheless about three times the capacity actually added in the
Tenth Plan.
The revised targets of capacity addition during Eleventh Plan, source-wise,
are as under:
(in MW)
Sector Hydro Thermal Nuclear Total
Central 2,922 14,920 3,380 21,222 (34%)
State 2,854 18,501 - 21,355 (34%)
Private 2,461 17,336 - 19,797 (32%)
Total 8,237 50,757 3,380 62,374 (100%)
13.21% 81.37% 5.42%
At the time of independence, the Generation Installed Electric Power
Capacity in India was only about 1.5 Giga Watt (GW). The power sector has
registered significant progress since the process of planned development of
the economy in 1950. The installed electric power capacity of the country
as of 31st March 2011 stood at a total of 174 GW excluding captive
generating capacities.
The Generation Installed Capacity Mix as on 31st March 2011 is as under:
Source Capacity (MW) % Share
THERMAL 112824 64.98
COAL 93918 54.09
GAS 17706 10.19
DIESEL 1200 0.70
NUCLEAR 4780 2.80
HYDRO 37567 21.61
(Renewable)
RES (MNRE) 18455 10.61
TOTAL 173626 100.00
Electricity generation from the power utilities in the country increased
from a mere 5.1 Billion Kilowatt hours (BkWh) in 1947 to 811 BkWh in 2010-
11. The total electricity generation in the country during 2010-11 was 811
Billion Units (BUs) registering a year-to-year growth of around 5.5%.
The break-up of generation during 2010-11 is as under:
Category A B C D E
Thermal 690.9 664.9 96.24 640.5 3.81
Nuclear 22.0 26.3 119.48 18.6 41.04
Hydro 111.4 114.3 102.64 103.9 10.01
Bhutan Import 6.5 5.6 85.68 5.4 4.69
Total 830.8 811.1 97.63 768.4 5.55
A = Target 2010-11 (BU)
B = Actual 2010-11*
C = % of Target
D = Actual Last Year 2009-10 (BU)
E = Growth (%)
* Generation excludes generation from plants up to 25 MW Capacity.
The electricity supply is, however, insufficient to meet the demand. The
country's prevailing energy deficit is 8.5% and the peak capacity shortage
is 10.3%. The per capita consumption of electricity increased from 15 kWh
in 1950 to about 700 kWh. The Integrated Energy Policy of the Government of
India forecasts that the growth of per capita electricity consumption in
India is expected to rise about four times from 700 kWh to 2500 kWh by
2032.
To meet the increasing energy requirements, the Integrated Policy projects
the need for an installed capacity of about 778 GW by the year 2032 for a
growth rate of 8%, of which nuclear power is envisaged to be about 63 GW by
2032 representing around 9% of the total installed capacity of the country.
Nuclear Scenario Post Fukushima Incident
An earthquake of magnitude 9.00 Richter scale hit northeast Japan on 11th
March 2011 followed by tsunami of 14 to 15 meter high at Fukushima Reactor
site beyond the design basis.
This earthquake affected nuclear power plants at four sites (Onagawa 1, 2
and 3; Fukushima Dai-ichi 1, 2, 3, 4, 5 and 6; Fukushima Dai-ini 1, 2, 3
and 4; and Tokai 2). All the operating units at the time of earthquake were
automatically shut down. However, at Fukushima Dai-ichi, the offsite power
loss during earthquake was followed with loss of onsite power as the diesel
generators for units - 1, 2, 3 & 4 were inundated by tsunami which
followed. The decay heat could not be removed leading to extensive damage
to the reactors and uncontrolled release of radioactivity followed.
With the timely execution of emergency plan, no significant health effects
to the workers and public have been reported.
NPCIL has been closely monitoring the evolution of the event at Fukushima
and getting information from International Agencies like International
Atomic Energy Agency (IAEA), World Association of Nuclear Operators (WANO),
Japan Atomic Industrial Forum (JAIF) and NPCIL representative posted at
WANO Tokyo Centre.
The safety review of Indian NPPs post Fukushima incident -
i) Considering the severity of the incident, proactive action of
constituting four task forces - one each for different generations of
designs of reactors - was taken. Indian Nuclear Power Plants consist of two
Boiling Water Reactors and eighteen Pressurized Heavy Water Reactors, with
three types of designs. Additional task forces reviewed the plants under
construction, namely VVERs at Kudankulam and 700 MW PHWRs at KAPP-3&4 and
RAPP-7&8.
The review and re-evaluation by the task forces as mentioned above re-
affirm adequate provisions to handle station blackout situation and
maintaining continuous cooling of reactor core for decay heat removal in
the event of extreme external natural events. Notwithstanding the above,
NPCIL has decided to reinforce the existing systems.
ii) Atomic Energy Regulatory Board has also constituted a high level
specialist committee for safety review of existing plants and its
recommendations would be implemented by NPCIL.
iii) Ministry of Environment & Forests, Government of India, has
constituted a committee to assess impact of tsunami and how it can be
mitigated.
Global Nuclear Power Scenario
Commercial nuclear power generation in the world is a mature, established
technology, having accumulated over forty years of successful operation.
There are 440 nuclear power reactors in the world with an installed
capacity of about 375 GW having 14436 reactor-years of cumulative
experience. Nuclear power accounts for around 14% of world's electricity
generation.
Post Fukushima incident, the initial apprehensions about nuclear power have
subsided and world over there is a clear reconfirmation of the inherent
safety of nuclear power.
With initial exaggerated concerns having given way to a sober return of
confidence based on facts rather than misconceptions, the world community
has reposed its faith in nuclear power, as several countries are in the
forefront to implement their own nuclear power programmes.
Environmental Impacts of Nuclear Power
While SPM, CO2, SOx and NOx, emissions and waste disposal are dominant in
the context of generating energy from fossil fuels, safety of environment
against radiation is a specific concern unique to nuclear power.
Environmental risks that are taken care of at various stages of the nuclear
fuel cycle are - mining (accidents, release of radon gas and radioactive
dust from Uranium mines and mills), radioactive seepage from waste and land
degradation, processing (accidents), transport (accidents, risk of
proliferation), and electricity generation (risk of catastrophic accidents,
low and high level radioactive wastes).
Additionally, decommissioning of nuclear plants entails the disposal of
radioactive wastes. Significant technological development has been made in
the area of radioactive waste disposal and decommissioning. There is time
in India for commercial deployment of these back-end activities. They are
yet to be proven at large enough scale to satisfactorily resolve economic
issues. The global data suggests that of all the conventional energy
options, nuclear energy has posed the least risks in terms of mortality per
billion megawatt hours of generation.
Role of Nuclear Power and Potential in India
India's nuclear power programme evolved in three stages to utilize modest
uranium and large thorium reserves in the country for electricity
generation. The first stage is based on Pressurised Heavy Water Reactors
(PHWRs), using natural uranium as fuel. This stage yields plutonium, which
forms the basis of development of the second stage, using plutonium along
with thorium in Fast Breeder Reactors (FBRs). This stage yields more
plutonium and an isotope of uranium. In the third stage, advanced power
reactors based on Uranium-Thorium cycle are envisaged for deployment.
The Integrated Energy Policy (2006) of the country recognizes that nuclear
energy offers the most potent means to long-term energy security. India has
to successfully realize the three-stage development programme and thereby
tap its vast thorium resources to become truly energy independent beyond
2050. The commercial deployment of thorium requires a significant capacity
of FBRs and development of technologies for thorium utilization. This
requires time and therefore capacity addition through import of large
capacity Light Water Reactors (LWRs) with fuel assumes importance. As per
the said policy, country's energy requirement, considering 8% growth in
GDP, will be 3880 BUs by 2031-32 needing an installed capacity of 778 GW.
The projected nuclear power capacity by the year 2032 is at 63 GW.
Nuclear energy has significant potential and, in the long run, the rapid
depletion of India's fossil resources makes the country's nuclear fuel
resources (natural uranium plus large thorium reserves) an important future
energy source. In the short-term, nuclear power already enjoys a locational
advantage in regions that are far from India's coal bearing areas. Nuclear
power is a clean, compact, reliable, safe, environmentally benign, devoid
of Green House Gas (GHG) emissions and economically viable source of power
generation.
The present share of nuclear power in the country's power scenario is 2.8%
which needs to be raised to about 8% in the next two decades and gradually
to 25% by 2050. This would necessitate augmentation of capacity and
capability in several areas of nuclear power technology encompassing Sites
for nuclear power plants, industrial infrastructure, capability and
capacity in manufacture and supply of exacting-standard equipment and
supplies, human resource development and so on.
COMPANY OVERVIEW Role of NPCIL
With the formation of Nuclear Power Corporation of India Limited in 1987 as
a Central Public Sector Enterprise under the aegis of Department of Atomic
Energy in India, the nuclear power generation moved to the commercial
domain.
NPCIL has attained maturity in the first stage of nuclear power programme.
Today, NPCIL is unique in having comprehensive capacity in the various
facets of nuclear technology viz. site selection, design, construction,
commissioning, operation & maintenance and life extension of nuclear power
plants.
Nuclear Power Plant Operations
Given the mandate of expanding the nuclear power base within the country,
as per the plans and schemes of the Government of India, NPCIL owns and
operates a fleet of 19 nuclear power reactors, in addition to operating the
Rajasthan Atomic Power Station Unit-1 on behalf of DAE. A very high
availability factor, one of the yardsticks for measuring operational
efficiency of a nuclear power plant, sets apart the nuclear power reactors
of NPCIL. The overall availability factor of operating stations for the
year 2010-11 was 89%.
The year 2010-11 recorded the highest nuclear power generation since the
inception of the Company. The generation and capacity factor during the
year under report were 26472 MU and 71% respectively as against 18803 MU
and 61% respectively last year. This is an increase in generation by 41%
over the last year resulting from improved fuel availability from both
indigenous and imported sources.
There are 10 reactors under IAEA Safeguards using imported fuel. They are
TAPS-1&2, RAPS-1&2, RAPS-3&4, RAPS-5&6 and KAPS-1&2. The total capacity
under safeguards stands at 1940 MW.
TAPS-2 of the first pair of commercial nuclear power reactors in the
country registered 590 days of continuous run, which is a record in the
operation of Indian nuclear power reactors. Eight reactors viz. KAPS-1 (372
days), RAPS-4 (373 days), RAPS-3 (404 days), KAPS-2 (406 days), MAPS-2 (432
days), KGS-1 (487 days), KGS-2 (529 days) and TAPS-2 (590 days) have so far
recorded continuous run of more than a year. Earlier, KAPS-1 became the
first Indian nuclear power reactor operating uninterrupted for more than a
year (372 days), fulfilling the long cherished target of operating a
nuclear power plant continuously without any outage from one mandatory
shutdown to another.
Capacity Addition
NPCIL added a capacity of 220 MW by completion of Kaiga-4 during the year,
increasing its capacity base from 4460 MW to 4680 MW. Kaiga-4 became the
20th nuclear power reactor of the country. Kaiga-4 is the last unit in 220
MW size series. Ongoing and future PHWR projects are of 700 MW unit size.
Renovation and Modernization
Enmasse Coolant Channel Replacement (EMCCR) and Enmasse Feeder Replacement
(EMFR) together with upgrades have been carried out at NAPS-2 and KAPS-1
and were synchronized to grid.
Status of Ongoing Projects
The work on Kudankulam (KKNPP) Unit-1 is nearing completion. KKNPP-2 is
under an advanced stage of construction. These units are expected to
commence operations in the year 2011 and 2012.
The work on two other ongoing projects, KAPP-3&4 and RAPP-7&8 comprising of
indigenous 700 MW PHWRs are progressing. These projects are expected to be
completed by 2017 with a capacity addition of 2800 MW.
New Projects
Steps in respect of implementation of bio-diversity conservation plan as
advised by the Ministry of Environment & Forests, Government of India are
initiated for Jaitapur site. In respect of KKNPP-3&4, the site has been
made ready in all respects to take up execution works. The CRZ clearance is
awaited.
Capacity Addition through International Cooperation
Early Work Agreements (EWAs) have been signed with AREVA, France in respect
of JNPP-1&2 (2 x 1650 MW) and Atomstroyexport, Russian Federation for
KKNPP-3&4 (2 x 1000 MW) for expeditious project implementation.
Pre-Project Activities at New Sites
Pre-project activities including geo-technical studies, the process of
obtaining environmental clearance, land acquisition and so on, at four new
green field sites viz. Gorakhpur in Haryana and Chutka in Madhya Pradesh
for indigenous 700 MW PHWRs and Kovvada in Andhra Pradesh and Mithi Virdi
in Gujarat for setting up 1000 MW plus LWRs based on international
cooperation have been commenced.
Export of Nuclear Reactors
NPCIL is open for export of 220 MW and 540 MW PHWRs known as small and
medium size reactors, bearing the stamp of Indian ingenuity, which could
prove to be optimal power solutions for countries where medium size
electricity grids are in operation and are keen on expanding their power
base.
MOU Performance
The expected MOU rating for the year 2010-11 is 'Very Good'. With the
availability of imported fuel for reactors under IAEA safeguards and
improved fuel supply from indigenous sources, NPCIL surpassed the
generation target in the year 2010-11.
Power Tariffs
The tariffs of electricity generated from atomic power stations are
finalized and notified by DAE in consultation with Central Electricity
Authority. Atomic power stations have been following single part tariff
structure taking into account the stipulated norms for technical and
financial parameters. The pricing is based on the Return on Equity method.
The average tariff of NPCIL stations during the year was Rs. 2.49 paise/kWh
(as against Rs. 2.30 paise/kWh for 2009-10). The variation is due to fuel
adjustment charges.
Challenges
Nuclear Power is inherently a high technology enterprise and that is the
fundamental reason for not many countries having it. Its dual use
capability, of its being used for producing devices capable of mass
destruction, has also led restrictions in its extensive development.
Although the inevitability of nuclear option is now universally accepted,
there exist some associated challenges. These emerge mainly from the public
perception of risks associated with nuclear power, which are
disproportionately higher than the actual risks. These include safety,
radio-active waste management, costs and other perceived risks like effects
on health, security and proliferation.
The most important challenge that has emerged at present is to address the
perception of the public, policy makers, planners and other strata of the
society about safety of nuclear power, in the wake of Fukushima incident in
Japan. However, recognizing this aspect, NPCIL has taken several additional
measures in the Public Awareness, with a multi-pronged approach for
effective enhancement of public perception about nuclear power. This
comprises structured public awareness and communication campaigns, outreach
activities to disseminate authentic information about safety, radiation and
other related aspects of nuclear power in a transparent manner to various
groups.
The availability of infrastructure for supply-chain and project execution,
sites, human resource and investments are the other key challenges in
implementation of the programme. Ensuring a smooth supply-chain and
projects execution, capacity and capability enhancement of Indian industry,
adequacy and appropriateness of the human resource and appropriate
partnerships for investment for the power programme are the key focus
areas. NPCIL has identified and initiated anticipatory actions in this
regard. Although challenges ahead are many, the outlook for nuclear power
remains positive.
OUTLOOK
Globally, fossil fuels will remain the dominant source of energy till 2030.
As fossil fuel resources are not renewable, the worldwide energy mix of
today will prove to be unsustainable. Therefore, industry experts are
supporting increased adoption of nuclear and renewable energy as well as
increased use of energy efficiency techniques.
The country's nuclear power programme ahead to realize rapid nuclear power
capacity addition provides robust outlook for NPCIL. With the improved fuel
availability from domestic international sources (for reactors under
safeguards in accordance with the Separation Plan) and the construction of
two reactors under advanced stages of completion, the generation is
expected to increase progressively in future.
NPCIL plans to launch by 2012 additional in-house designed 4 x 700 MW PHWRs
(Four have already been launched) and 10 LWRs having capacity of 10000 MW
with International Cooperation. As per the long term plan of the Company,
by 2032, LWRs upto the capacity of 40000 MW is expected to be launched. To
conclude, at present, NPCIL is poised for meeting national expectations of
rapid nuclear power capacity addition in the country.
HUMAN RESOURCE MANAGEMENT
NPCIL Parivar consists of 11834 strong and dedicated workforce with 3414
Engineers and Scientists, 5784 technical employees, 381 non-technical
executives and staff and 2255 Auxiliary support staff such as paramedical
service, fire service, etc., who spearhead the activities of the
organization. NPCIL's workforce includes 1091 women employees.
The group-wise staff strength consists of 4065 in Group A, 3301 in Group B
and 4468 in Group C categories of employees.
All HR initiatives are directed towards achievement of organizational goal
of attracting, motivating and retaining the precious asset i.e. Human
Resource. These measures included developing strategic and incremental
packages from time to time for effective Human Resource Management to meet
the aspirations of the employees.
The implementation of the Sixth Pay Commission in all the areas which are
in line with the Government orders has paved way to improvise the existing
working conditions, facilities and benefits. It has created significant
impact in reduction of attrition rate in NPCIL.
Optimization of manpower continued to be an important strategy towards best
utilization of human resource. Accordingly, staffing has been done strictly
in accordance with the optimized manpower models for Projects, Stations and
Headquarters, including multi-unit Sites.
Training and Development initiatives covered competency development for
fresh as well as experienced manpower across hierarchy. Besides, well
developed internal training programmes, customized management development
programmes with the involvement of professional training institutes and
experts were organized for higher levels. 2426 man-days of training was
imparted during the year. 34 employees were also sponsored for acquiring
higher education in Technology, Management, etc. Students of reputed
colleges were imparted practical training in different engineering and
management disciplines to meet their curriculum requirements.
During the year, as a part of annual induction programme of young blood to
the Organisation, 110 posts in Scientific category for NPCIL Batch-18, 80
direct recruits in Scientific categories and 47 posts in the non-technical
categories (Group - A & B) were filled through centralized recruitment
process. In the career progression front, 856 employees in Scientific and
Technical categories, 162 (82 executives and 80 non-executives (HQs) in
non-technical categories were elevated to next higher grade. Design and
development of online portal for inviting online applications for
nontechnical executive posts were undertaken. Existing system of Annual
Confidential Report (ACR) was modified to electronic Annual Performance
Assessment Report system (eAPAR).
Employee Relations
Harmonious Employee Relations prevailed in all the Stations, Projects and
Headquarters. Regular meetings were held with the recognized Unions at
Station/Project levels and with the Joint Consultative Council at the apex
level to discuss and resolve the various employees' related issues. The
harmonious employee relations are a result of sound and constructive
participative approach adopted by Management in decision making in matters
affecting the general welfare and service conditions and conflict
resolutions based on mutual understanding, which resulted in increased
production and productivity.
A structured mechanism for redressal of grievances is in operation which is
sensitive and attentive to employee grievances at all levels. The pension
grievances registered in CPENGRAMS, a website of Department of Pension and
Pensioner's Welfare were attended immediately.
Achievement by Stations
TAPS-1&2, KAPS, RAPS-3&4 and TAPS-3&4 qualified as Excellent Performing
Stations during the year and a reward of Rs. 2,000/- was sanctioned to each
employee of the above Stations.
MAPS and RAPS-3&4 achieved longest continuous run of 432 days and 404 days
respectively and the employees of the stations have been sanctioned a
special reward of Rs. 4,000/- each.
Continuous run of Industrial Accident Free Period was achieved by RAPS-1&2
and Kaiga-3&4 and the employees were given a memento.
Employee Participation
Successful negotiations and participation of Employees' Unions have led to
finalisation of NPCIL Performance Linked Incentive Scheme in NPCIL.
Decentralised Certification of Standing Orders with regard to NPCIL and its
Units have been taken up and the Standing Orders in respect of Headquarters
and TAPS-1&2 have been duly got certified during the year.
Industrial Dispute raised by NAPS Union on new Allotment policy was
mutually settled.
Other Welfare Measures
Enhancement of insurance coverage and premium thereof was carried under
NPCIL (Employees Group Savings Linked Insurance) Scheme and one more option
to the left over employees to become members of the Scheme was extended and
a total of 11,419 employees have become members under the revised coverage.
Grant of payment of ex-gratia has been effected to the families of 24
deceased employees.
FINANCIAL REVIEW
Results of Operations (Profit and Loss Statement Analysis)
Total Income
The total income comprises of income from sale of electricity, consultancy
services and interest earned on investments of temporary surplus in term
deposits with banks and bonds. The total income for FY 2010-11 is Rs. 6898
crore as against Rs. 4479 crore in the previous year registering an
increase of 54%.
Sale of Electricity
The Company's bulk customers are electricity utilities owned by State
Governments and Union Territories. Revenue on sale of electrical energy is
recognized net of levies.
Income from sale of electricity for the FY 2010-11 was Rs. 6016 crore which
constituted 87% of the total income. The income from sale of electricity
has increased by 58% over the previous year's income of Rs. 3807 crore.
Electricity generation, as per the billing cycle, in 2010-11 has been 26469
MUs as against 18798 MUs in 2009-10 showing an increase of 41%. The revenue
realization has been maintained at a high level of 99%.
Other Income
The Company's other income in the FY 2010-11 was Rs. 882 crore as compared
to Rs. 672 crore in the FY 2009-10 indicating an increase of 31%. The
average yield on investment is around 8.80% during the year under report.
Total Expenditure
Total expenditure of the Company consisting of Operating & Maintenance
Expenditure, Interest and Depreciation was Rs. 5210 crore as against Rs.
3791 crore in the previous year registering an increase of 37%.
Expenditure related to operations
The expenditure incurred on fuel & heavy water, operation & maintenance,
employees' remuneration, administration and other expenses for the FY 2010-
11 was Rs. 3680 crore which is around 40% more than the expenditure of Rs.
2629 crore incurred during the previous year. The fuel charges and heavy
water charges were Rs. 1670 crore and Rs. 622 crore as against Rs. 972
crore and Rs. 446 crore for the previous year. This increase is mainly on
account of increase in level of operations. It is noteworthy that the year
2010-11 recorded the highest electricity generation since the formation of
the Company.
Interest Charges
Interest charges (excluding Interest During Construction period) consist of
interest amount on long term borrowings. The average interest cost is
around 7.74% for the year 2010-11. Interest charges stood at Rs. 662 crore
for the FY 2010-11 as compared to Rs. 441 crore in the previous year.
Depreciation
As per the accounting policy of the Company, depreciation is provided on
straight line method on the capitalized cost at the rates specified in
Schedule XIV of the Companies Act, 1956 except for computers and
peripherals where depreciation is charged @ 19% and for software where
depreciation is charged @ 20%. Cost of computers and peripherals are
depreciated on straight line method over a period of 5 years to the extent
of 95% and software to the extent of cent percent. With the capitalization
of Unit-4 at Kaiga, Renovation & Modernization actions in NAPS-2 and KAPS-1
namely EMCCR, depreciation was higher at Rs. 868 crore in FY 2010-11
compared to Rs. 721 crore in the previous year registering an increase of
20%.
Profit Before Tax, Provisions and Prior Period Adjustments
The profit of the Company before tax, provisions and prior period
adjustments for the FY 2010-11 was Rs. 1688 crore as compared to Rs. 688
crore in the previous year.
Prior Period Adjustments
Prior period items are incomes or expenses which arise in the current
period as a result of 'errors' or 'omissions' in the financial statements
prepared in earlier years. Effects of changes in estimates are not treated
as omission or error. For the FY 2010-11, prior period adjustments amount
to Rs. 1 crore.
Provision for Taxation
An amount of Rs. 311 crore has been provided towards current Income-tax
under Minimum Alternate Tax provisions and Wealth Tax.
Profit after Tax
Inspite of the factors affecting operational revenue, the Company has
earned a Profit After Tax of Rs. 1376 crore during FY 2010-11 as compared
to Rs. 416 crore in FY 200910. The surge in profits is due to higher
capacity utilization resulting in increased generation of electricity.
Financial condition (Balance Sheet Analysis) Networth
The networth of the Company at the end of FY 201011 increased to Rs. 22162
crore from Rs. 21268 crore in the previous year, registering an increase of
4% mainly due to retained earnings. Correspondingly, the Book Value per
share also increased to Rs. 2184 from Rs. 2096.
Loan Funds
The loans as on 31st March 2011 were Rs. 17909 crore in comparison to Rs.
15462 crore as on 31st March 2010, registering a growth of 16%. A summary
of the loans outstanding is given below:
(Rs. in crore)
As at As at
31st March 31st March
Details 2011 2010
Bonds 2854 3001
Term Loans from Banks 9186 6186
Sub-Total 12040 9187
Unsecured Loans
Loans from Government of India 5870 6275
SuB-TOTAL 5870 6275
As per the plan of allocation approved by the Government of India, the
Company raised a sum of Rs. 3000 crore during the year for its various
projects viz. RAPS-7&8, KKNPP-1&2 and KAPP-3&4 by availing term loans from
Public Sector Banks as mentioned under:
(Rs. in crore)
State Bank of India 1250
Bank of India 1500
Dena Bank 250
The Company has redeemed Bonds amounting to Rs. 148 crore during the year.
During the year 2010-11, the Company availed Rs. 34 crore of Unsecured Loan
(Russian Credit) from Government of India. The Company has repaid Rs. 450
crore to the Department of Atomic Energy, Government of India, as per the
Inter Governmental Agreement towards the loan (Russian Credit) availed from
the former. Balance of Unsecured Loan (including Russian Credit) has been
reduced by Rs. 405 crore during the year 2010-11. Reduction is due to the
repayment to DAE and reduction in Foreign Exchange Rate Variation. The
final balance of Unsecured Loan as on 31st March 2011 is Rs. 5870 crore.
DAE loan (Russian Credit) represents funds provided by DAE to deposit with
Controller of Aid Accounts & Audit (CAA&A) for repayment of credit extended
by Government of Russian Federation to Government of India, after repayment
in terms of various contracts entered into with M/s. Atomstroyexport to set
up two units of 1000 MW each at Kudankulam, with an understanding that
exchange fluctuation on repayment of the credit by Government of India
shall be on account of the Corporation.
Fixed Assets
The Company's gross block increased from Rs. 19231 crore in FY 2009-10 to
Rs. 21337 crore representing a growth of 11%. This is mainly on account of
capitalization of Kaiga Unit-4 and Renovation & Modernization activities
carried out in NAPS-2 and KAPS-1.
Investments
The investments consist mainly of power bonds, equity participation in
joint venture viz. M/s. L&T Special Steels & Heavy Forgings Pvt. Ltd. to
produce special steels and ultra heavy forgings and Bharatiya Nabhikiya
Vidyut Nigam Ltd., a Company under the same management, NPCIL Employees'
Group Leave Encashment Scheme with LIC of India, SBI Life Insurance Co.
Ltd. and NPCIL Employees' Gratuity Schemes with LIC of India and SBI Life
Insurance Co. Ltd.
During the year, the Company has not made any non-trade investments.
Total investments stood at Rs. 2290 crore as on 31st March 2011 as against
Rs. 2413 crore as on 31st March 2010.
Working Capital
Current Assets after netting off current liability i.e. net working capital
stood at Rs. 9632 crore as on 31st March 2011 as against Rs. 7084 crore as
on 31st March 2010.
Credit Rating
The Company's Bonds have been accredited with a 'AAA' rating indicating
highest safety from both CRISIL and CARE since FY 2001-02 onwards.
Risk Management
Enterprise Risk Management Policy has been formed for identification of key
risk areas and formulate appropriate risk mitigation plans for taking
corrective action in a time bound manner.
Internal Control System and their adequacy
The Company has adequate internal control system commensurate with the
nature and size of business which meets the objectives of efficient use and
safeguarding of resources, compliance with statutes, policies and
procedures and maintaining accuracy of recording of transaction and
reporting the same promptly. The scope of internal audit involves
examination and evaluation of the adequacy and effectiveness of the system
of internal accounting, system and procedures and other operational areas.
Independent firms of Chartered Accountants who are appointed with the
approval of the Audit Committee carry out the internal audit. The
observations raised out of the audit are subject to periodic review and
compliance monitoring by Audit Committee.
Financials at a Glance
The financial performance of NPCIL for the last 10 years along with the key
financial ratios is summarized as 'Performance at a Glance'.